  • Working without permits so far. Apparently the inspector quit and they don't have a replacement yet to get all the permits signed and out. Who knows how long that will take.
  • The dumpster is gone.
  • The entire upstairs is gutted.
  • The HVAC guys started running the vents to the 5 formerly 3 rooms. They also put in a much needed attic fan.
  • The man may go and order winders.
  • Guy installing winders is coming tomorrow to assess.
  • Some electric will be done tomorrow.
  • Walls will start going up tomorrow. Hopefully the man will work slowly to ensure straightness and plumb. He tends to rush through things sometimes and is a little ADD.
  • Shopping for bathroom fixtures is Saturday.
  • Plumber is coming sometime next week to start.